Analyzing Factors Affecting the Delay in Building Construction Projects in Sri Lanka through the Interaction of the Project Team

View/ Open
Date
2022-09Author
Muthumalki, GAT
Jayasooriya, SD
Kawmadi, WN
Lakmal, AH
Metadata
Show full item recordAbstract
Constructions	undergo unfavourable	situations related	to	their	cost	overruns	due	to	
the	 delays and	 exposure	 to	 risks because	 of	 inappropriate	 identification	 and	
minimising	 of	 the	 factors.	 To	 fulfill	 this	 gap,	 the	 research	 has	 analysed factors	
affecting	 the	 delay	 in	 building	 construction	 projects	 in	 Sri	 Lanka	 through	 the	
interaction	 of	 the	 project	 team	 with	 an	 adequate	 understanding	 on	 the	 practical	
solutions	for	minimising relevant	factors.	The	study	has	used	a	mixed	approach	of	
qualitative	and	quantitative	techniques	for	the	identification	of	factors,	and	a	review	
of	literature	was	done.	To	assess	the	 factors	affecting	delays,	a	questionnaire	was	
distributed	 among	 40	 professionals	 in	 Sri	 Lanka	 and	 the	 analysis	 based	 on	 the	
Relative	 Important	 Index	 (RII)identified	 that	 client	 related	 factors,	 contractor	
related	factors,	consultant	related	factors	and	other	related	factors and	assessment	
of	 the	 factors	that	affect	 the	 building	 construction	industry.	Significant	 factors	 of	
building	 construction	 delays	 were	 identified	 such	 as	 poor	 communication	 and	
coordination,	delays in	obtaining	approvals	from	government	regulated	bodies	and	
delays	 in	 subcontractor	 activities,	 inexpedient	 scheduling	 and	 project	 planning,	
inefficient	contractor	work	and	unexpected	subsurface	conditions	and	unforeseen	
circumstances.	 The	 study	 identified	 that	the	 contractor	 related	 category	 had	 the	
highest	affect	as	a	result	of delays	of	construction	industry	in	Sri	Lanka.	To	identify	
practical	 solutions	 for	 minimising,	 interviews	 were	 conducted	 by	 selecting	 10	
professionals	 with	 more	 than	 10	 years	 of	 experience	 as	 the	 sample.	 Concerning	
more	 on	 the	 effective	 performance	 of	 the	 key	 stakeholders	 under	 a	 better	
management	 system	 is	 recommended	 in	 minimising	 the problem	 of	 increasing	
delays,	which	will	help	to	ameliorate	performance	issues	of	the	industry.